DUSHANBE, May 2, Asia-Plus -- Russian aluminum giant “Russian Aluminum” (RusAl) and Tajikistan’s government have not yet reached compromise on a type and height of the Roghun dam, the Barqi Tojik holding company head Sharifkhon Samiyev told journalists on April 28.
According to him, the project is currently under consideration of independent experts, who are supposed to prepare their resolution by late June this year.
We will recall that the Tajik side has designed a 335-meter high fill dam, while specialists from RusAl insist on the construction of a concrete dam.
Speaking on this issue, Mr. Samiyev termed the 300-meter high fill dam of the Norak power station as an example. He noted that the Norak dam had successfully passed all kinds of tests and sustained 9,000 tremors of different magnitude since the time when it was put into operation.
DPT’s leader replaced
Emomali Rahmon holds talks with his Russian counterpart in Moscow to discuss cooperation
Tajik leader participates in events dedicated to 79th anniversary of Victory over Nazi Germany
Congratulations on Vicotry Day
The world's most popular sport now has its own day for fans to celebrate — May 25
A conference expected to be held in Dushanbe next week to discuss once again the media law on media
Iran can serve as gateway for Central Asian countries to internal markets, says Iranian ambassador to Tajikistan
Another incident with use of firearms occurs on Tajik-Kyrgyz border
All five Central Asian leaders to attend Victory Day events in Moscow
Tajikistan ranked 1550th out of 180 countries and territories in terms of press freedom
All news
Авторизуйтесь, пожалуйста