DUSHANBE, January 19, 2011, Asia-Plus -- In 2010, more than 1.6 billion somoni (equivalent to more than 363 million U.S. dollars) were spent for construction of hydropower facilities in Tajikistan, according to the Ministry of Energy and Industries (MoEI).
The source at a MoEI says this amount includes 690 million somoni (43 percent) of state and enterprises’ funds and 916,600 million somoni (57 percent) of foreign loans.
“49.7 million somoni were spent for construction of the Sangtuda-1 hydroelectric power plant (HPP) and 544.8 million somoni (a 37.6 million contribution of Tajikistan and 507.2 million somoni provided by Iran) were spent for construction of the Sangtuda-2 HPP,” the source said.
He added that 554.7 million somoni were spent last year for completion of construction of the Roghun HPP, which was 123.6 million somoni more than in 2009. We will recall that the 2010 national budget earmarked 650 million somoni for Roghun’s construction.
Meanwhile, the national budget for 2011 projected 1.22 billion for enhancement of the energy sector, including 850 million somoni earmarked for completion of construction of the Roghun HPP.
Islamic banking and finance is emerging in CIS member nations
Emomali Rahmon holds meeting with Tajiks living in Italy
Deputy head of Shahritous district detained on suspicion of bribery
Precious metals and gems account for 48.5% of Tajikistan’s total exports in Q1 this year
Tourism Development Committee releases the 2nd report on the risk of plague; this time, it says the risk is minimal
Eight members of Tajik opposition group detained in Rome
Tajikistan-Italy investment forum result sin signing of contracts worth more than US$160 million
Emomali Rahmon meets with WeBuild Group CEO in Rome to discuss the progress of construction of Roghun HPP
The population of Central Asia expected to exceed 1000 million by 2050
Tajikistan authorities warn about the risk of appearance of the plague in the country
All news
Авторизуйтесь, пожалуйста